- ENERGY

Transformer station Lines and Urbanization, New South Resistencia - Chaco - Argentina

  • Completion: 2023
  • Client: Ministry of Planning, Economy and infrastructure of the province of Chaco
  • Location: Resistencia Chaco (Argentina)

The work will be done with in the erection of a line of medium-voltage of 33 kV double triplet, which starts in the distribution center N° 22 (Transformer Station Vilela) in the city of Resistance, and passes through the southern area of the city.

It is mounted intermediate the line referred to two transformer station that will benefit with a power transformer 16 MVA each one of them and will have rooms of cells, respectively, for the wiring of the inputs and outputs of distribution lines.

To run the assembly lines of medium voltage single triplet 13.2 kV corresponding to the distributors of the stations that will include 34 Mushrooms with transformers of 400 KVA.

7.534 m

length

332.602 m3

embankment

94.479 tn

asphalt

4.579 m3

concrete

– Construction and commissioning of service distribution centers 33/13.2 kv with transformadores16 mva 33/13.2 kv: 2 a
– Substation transformers aerial 400kva: 34 a
– Underground cables: 90000 ml
– Fill: 10000 m3
– Supply, installation and commissioning of power transformers 16mva: 2 a
– Supply and installation of switchgear primary medium-voltage: 40 a
– Reinforced concrete: 800 m3